CASE STUDY

Early Warning Flags Risk To Reaching
The Critical Milestone

Project

Aberfeldy Village is located in London’s East India Docks area and is composed of a selection of studio, one and two-bed apartments. EcoWorld was acting as the
developer and main contractor on this project. Buildots solution was deployed on two blocks consisting of 223 apartments and 1500 sqm of commercial space.

Challenge

EcoWorld saw the need for better visibility and quality control in securing the ‘watertight’ milestone as it has a huge impact on the project delivery timeline. Unfortunately, the subcontractor fitting the windows was falling behind schedule, triggering a domino effect on other activities and potentially causing major delays.

Quote Ecoworld3
logo Ecoworld (1)

EcoWorld London creates outstanding and sustainable developments that aim to stand the test of time. The business is a part of EcoWorld International, a real estate developer listed on the Main Market of Bursa Malaysia Securities Berhad.

icons-Ecoworld

Buildots Solution

Buildots provided early warning to EcoWorld about the deviation from the schedule based on solid data helping to de-risk achieving the critical milestone. When it became clear why the subcontractor was falling behind, they initiated a more structured process and increased labour and run rate. As a result, the watertight milestone was achieved ahead of schedule.

Results

The subcontractor increased labour to stay on the critical path finishing 9 weeks ahead of schedule from a 65 week program.